Event 18

No-Cost Extension Request

Dr. Brown needs more time to complete remaining project activities. Marcus must review whether a no-cost extension is appropriate, whether enough approved work remains, and whether the remaining funds can support the extension period.

Year 3 Event 18 No-Cost Extension

Story Background

More time may be needed, but time must be justified

The project is approaching its scheduled end date. Much of the Community Access to Preventive Healthcare Initiative has been completed, but not everything is finished.

Dr. Brown wants additional time to complete final community outreach activities, finish data collection follow-up, receive final CHAN documentation, and prepare the project’s final reports.

She is not asking for additional funding. Instead, she wants to extend the project period so the remaining approved work can be completed using funds already awarded.

The question is not simply whether money remains. Marcus must help determine whether additional time is needed to complete approved project work and whether the request can be routed through the required sponsor process before the project period ends.

Trigger Issue

Dr. Brown asks about extending the project period

Training Concept

A no-cost extension adds time, not money

A no-cost extension extends the project period without adding new sponsor funds. It may be appropriate when more time is needed to complete approved project activities. It should not be used simply because money remains.

Project Period Extension

Additional time added to the approved project period so remaining work can be completed.

No Additional Funds

The sponsor does not provide new money. The project uses remaining awarded funds.

Remaining Work

The request should explain what approved project activities still need to be completed.

Remaining Funds Alone Are Not Enough

Having money left is not a sufficient reason to extend an award.

Justification

The request should explain why the extension is needed and how the time will be used.

Sponsor Requirements

The Notice of Award or sponsor guidance determines the process, deadline, required content, and approval path.

What Marcus Reviews

The request must connect time, work, and funds

Notice of Award

Identifies whether a no-cost extension is allowed and what sponsor approval process applies.

Project Timeline

Shows what activities are complete, what remains, and when the remaining work can reasonably be finished.

Remaining Funds Review

Confirms whether the project has enough unobligated funds to support the extension period after pending obligations are considered.

CHAN Status

Helps Marcus determine whether subrecipient work, invoices, final reports, or closeout documentation are still pending.

Final Deliverables

Identifies the reports, data, community activities, and closeout items that remain unfinished.

Extension Justification

Explains why additional time is necessary to complete approved work and how the extension period will be used.

Extension Review

Is the request justified?

No-Cost Extension Snapshot

Remaining work and remaining funds

Extension Review
Review Item Current Status Concern Marcus’s Review
Project end date Approaching Limited time remains Check request deadline
Remaining work Final outreach and data follow-up pending Must be approved project work Confirm scope
CHAN activity Final documentation still pending Subrecipient closeout may be affected Coordinate timeline
Remaining funds Available balance exists Funds must support extension activities Review budget

Marcus must show that the extension is needed for project completion, not just because the project has funds left.

Marcus’s Analysis

Questions before routing the request

What approved work remains?

Marcus confirms that the remaining activities are part of the approved project and not new scope.

Why was more time needed?

The request should explain the reason for the delay or unfinished work in a clear, factual way.

Can the funds support the extension?

Marcus reviews remaining funds, pending costs, payroll needs, subrecipient costs, and closeout expenses.

Does the extension affect reporting?

New reporting dates, final deliverables, and closeout timelines may change if the extension is approved.

Does CHAN need more time too?

If CHAN has remaining work, the subaward timeline may also need review.

What does the sponsor require?

Marcus checks the deadline, form, justification, signatures, and institutional routing path required before submission.

Decision Point

Should Marcus support routing the no-cost extension request?

Dr. Brown asks for additional time to complete final project activities. The project has remaining funds. What should Marcus recommend?

Resolution

Marcus prepares the request for review with a clear justification

Marcus determines that the request has a reasonable administrative basis because approved work remains, the remaining funds can support the proposed extension activities, and the request can be submitted before the sponsor deadline. The request still needs to follow the required institutional and sponsor process.

No-Cost Extension Review Notes

Prepared by Marcus Rivera

Issue Identified Dr. Brown requests additional time to complete remaining approved project activities without requesting additional sponsor funds.
Records Reviewed Notice of Award, project timeline, remaining funds report, pending obligations, CHAN status, final deliverables, and sponsor extension requirements.
Administrative Concern The extension must be justified by remaining approved work, not simply by the existence of unspent funds.
Recommended Action Prepare and route the no-cost extension request before the sponsor deadline, including justification, work plan, remaining funds explanation, and revised timeline.

A strong no-cost extension request explains what remains, why more time is needed, how existing funds will be used, and how the project will reach completion.

Common Misconceptions

What learners should not assume

“No-cost extension means free extra time.”

The extension must follow sponsor requirements and be justified by remaining approved work.

“Remaining funds are enough reason to extend.”

Remaining funds alone do not justify an extension. The project must need time to complete approved activities.

“We can request it after the award ends.”

Sponsors usually require extension requests before the project end date. Marcus must check the deadline and process early.

Year 3 Connection

An extension changes the closeout timeline

A no-cost extension can help the project finish responsibly, but it also affects reporting deadlines, subrecipient timelines, remaining funds, and closeout planning.

Final work plan

The team needs a clear plan for what will be completed during the extension period.

Remaining funds

Marcus must confirm that funds are sufficient and appropriate for the planned extension activities.

Closeout shift

If the sponsor approves the extension, final reporting and closeout dates will move.

Resources

References behind this scenario

These references show why no-cost extension requests require more than a remaining balance. A post-award research administrator should review the award terms, confirm what approved work remains, validate available funds, coordinate with the appropriate institutional office, and route the request through the sponsor’s required process before the current project period ends.

Notice of Award

The Notice of Award identifies sponsor-specific rules for project period changes, extension authority, request deadlines, required documentation, and approval conditions.

Connection to Event 18: Marcus must confirm the sponsor process before helping prepare or route the no-cost extension request.

2 CFR 200.308 — Revision of Budget and Program Plans

This section matters when a project needs changes to the approved budget, program plan, or project period. Depending on the award terms, a no-cost extension may require sponsor notification or prior approval.

Connection to Event 18: Marcus reviews whether extending the project period requires sponsor approval before the team continues work beyond the current end date.

Remaining Funds Report

A remaining funds report helps confirm whether unobligated funds are actually available after pending payroll, subrecipient costs, open obligations, final invoices, and closeout expenses are considered.

Connection to Event 18: Marcus reviews whether the remaining funds support the approved work planned for the extension period.

Extension Work Plan

An extension work plan explains what approved activities remain, why additional time is needed, who will complete the work, what timeline applies, and what deliverables will be completed during the extension period.

Connection to Event 18: the work plan explains why additional time is needed and shows that the extension supports approved project work, not new scope.